Monday, May 5, 2014

Facilities - 5th toilet for "Hoot and Wild orchid field" pitches. Construction

 Updates ongoing.
11.5.2014
Internal rain water collecting system

10.5.2014
Start of rain water collecting system into converted butterchurn


Reclaimed pine panels





6.5.2014
 Found plastic rubbish used as an impromptu .......

 ..... "dampcourse"

Progress on compost toilet


In situ




Very pleased with 5th compost toilet



 Integral plants






5.5.2014
Roof boards on, bitumen covered.


Start of compost toilet


Using reclaimed timber.
4.5.2014
Bench for washing up area.


Grass clippings enclosure



Building around the trees - Leaves already blending the building in to the woodland







3.5.2014 Dwangs




16.4.2014














Reclaimed pine  for door posts.